The project consists of reconstructing and widening the 13th Avenue East and Ninth Street East intersection to accommodate dual left turn lanes in all directions. The project will also involve the addition of a northbound through lane from 13th Avenue East to Seventh Avenue East, and upgrades to outdated/undersized utilities within project limits to minimize future disruptions.

Detour maps and final layout visuals were available and included in the presentation. Additional details are as follows:

Project Schedule

  • Begin Date: August 2017
  • Estimated End Date: November 2018
  • Percent Complete: 55%

Road Closures

Completed Work
  • Temporary traffic signals installed

Upcoming Work

  • Phase 1 (Spring 2018): Install additional northbound lane from 13th Ave. E. to Seventh Ave. E.