Sheyenne Street Segment 1 - 13th Ave. to Beaton Dr

Sheyenne Street Segment 1 Finished Section Rendering

About this Project:

Reconstruction of a five-lane road that includes two lanes in each direction and a center turn lane to ease congestion and safety concerns. Project work includes concrete paving, curb and gutter, shared-use path, city utilities, street lights and traffic signal improvements.

Estimated Construction Cost

  • $6 million

Estimated Special Assessments

Project Schedule

  • Estimated Begin: April 2018
    • Phase 1 completion – early July
    • Phase 2 completion – early September
    • Phase 3 completion – mid September
    • Phase 4 completion – early October
  • Estimated End: June 2019
  • Project complete: 90%

Completed Work

  • Underground
  • Paving
  • Curb and gutter
  • Sidewalks
  • Driveways

Current Work

  • Electrical work
  • Street light installation

Upcoming Work

  • Traffic signal installation
    • The temporary span wire traffic signal at 17th Avenue W. and Sheyenne Street is to be replaced with the permanent signal in early March. The contractor intends to complete the remaining street lights and then move onto the traffic signals. The permanent traffic signal will have left turn arrows.  
    • Temporary signals will be active at Beaton Drive late February/early March and the permanent will be delivered in September.
  • Final details